Traffic & Construction Updates

Print
Press Enter to show all options, press Tab go to next option

Rancho Santa Fe Boulevard at Dysart Road

The City of Avondale awarded a contract to Visus, Inc. to install a northbound to eastbound right turn lane from Dysart Road onto Rancho Santa Fe Boulevard. Improvements include new pavement, curb, gutter,sidewalk and traffic signals.

2020.1.22 - dysart rd map

Construction is scheduled to begin in January 2020. The project will take approximately four months to complete.

CONSTRUCTION AHEAD

Construction work hours typically will be 6 a.m. to 5 p.m.,Monday through Friday. Hours will vary with seasonal changes and construction crews may work evenings and weekends as needed.

TRAFFIC RESTRICTIONS

During the construction project,expect traffic lane closures and restrictions. Local access will be maintained for residents, businesses and emergency vehicles. Please note there will not be enough room for large semi-truck vehicles and buses to turn right (east) onto Rancho Santa Fe until the project is complete. Access will be provided for large trucks and buses via McDowell Road. Allow extra time when traveling through the work zone as there may be traffic delays.Thank you for your assistance and cooperation.

ABOUT THE PROJECT

The City of Avondale awarded a contract to Visus, Inc. to install a northbound to eastbound right turn lane from Dysart Road onto Rancho Santa Fe Boulevard. Improvements include new pavement, curb, gutter, sidewalk and traffic signals. The project is slated for completion in June 2020. Please subscribe to eNotifications to receive future updates.

FOR MORE INFORMATION

If you have questions or need more information about the intersection improvement project in your community, please call the project hotline at 602.264.4611 or subscribe to receive notifications at www.AvondaleAZ.gov/traffic for project updates.  We are here to answer your questions and assist you in any way that we can. The following notice was mailed to all businesses and stakeholders about enhancing neighborhood surroundings. 

PUBLIC NOTICE: Dysart/Rancho Santa Fe Intersection Improvement



2020.2.18 - I-10 closure map

 

I- 10 & Fairway Drive Interchange

Construction crews continue to make progress on the new traffic interchange on Interstate 10 (Papago Freeway) and Fairway Drive in the West Valley.

 Learn more about this project

 

Drivers should allow extra travel time and use caution in the work zone while the following activities take place:

  • Weekday work hours are 6:30 a.m.- 4:30 p.m.
  • The I-10 HOV lane closure in the project area is anticipated to continue until early April.
  • Several full closures of I-10 (Papago Freeway) are anticipated through spring.
  • Several intermittent ramp closures are anticipated through completion.
    The new traffic interchange at Fairway Drive is scheduled for completion in spring 2020. 

Crews are working on a $20.8 million project to construct an I-10 interchange at Fairway Drive in Avondale. The project, scheduled for completion this spring, is part of the Maricopa Association of Governments’ Regional Transportation Plan approved by county voters in 2004.

Dysart/Rancho Santa Fe Intersection Improvements Construction Scheduled

Post Date:01/22/2020

Avondale PublicInformationOfficeLongLogo                                                Media Release


Posted: January 22, 2020 

Dysart/Rancho Santa Fe Intersection Improvements Construction Scheduled

Dysart Road will see some ongoing construction starting this month, as part of the City of Avondale’s plan to improve traffic flow on this heavily traveled road. The City of Avondale awarded a contract to Visus, Inc. to install a northbound to eastbound right turn lane from Dysart Road onto Rancho Santa Fe Boulevard. Improvements include new pavement, curb, gutter, sidewalk and traffic signals.

Construction is scheduled to begin Monday, January 27, 2020. The project will take approximately four months to complete. Construction work hours typically will be 6 a.m. to 5 p.m., Monday through Friday. Hours will vary with seasonal changes and construction crews may work evenings and weekends as needed.

During the construction project, expect traffic lane closures and restrictions. Local access will be maintained for residents, businesses and emergency vehicles. Please note there will not be enough room for large semi-truck vehicles and buses to turn right (east) onto Rancho Santa Fe until the project is complete. Access will be provided for large trucks and buses via McDowell Road. Allow extra time when traveling through the work zone as there may be traffic delays.

If you have questions or need more information about the intersection improvement project in your community, please call the project hotline at 602.264.4611 or visit www.AvondaleAZ.gov/traffic  for project updates.  